CONSOLIDATED TEAM ACCOMPLISHMENTS BT2
#TeamKennyCordovero BT2 Team Members: K Cordovero, A Ferrer and R Distura Accomplished: Continued...
#TeamKennyCordovero BT2 Team Members: K Cordovero, A Ferrer and R Distura Accomplished: Continued...
#TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, R Daliva and A Ordas...
As scheduled: Morning From 5:00 AM to 7:00 AM Reason: NGCP temporary shut down of Panitan...
#TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice, R Degones and R Fuentes...
June 2-28, 2024, Month-long Diary #TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, R Daliva and A Ordas Accomplished: June 2, 2024, Sunday 1. Replacement of rotten pole/ conversion of structure and rehabilitation of 15 kilowatt hour meters at Barangay Angub, Cuartero w/ BT 11 June 3,…
June 30, 2024, Sunday As scheduled: Morning From 5:00 AM to 7:00 AM Reason: NGCP temporary shut down of Panitan Substation due to Annual Preventive Maintenance Servicing Activities. In actual: From 5:00 to 6:40 AM 6:42 AM – Closed Feeders D1, D2, and D3 6:43 AM – Closed Feder D4…
June 22-23 and 27-28, 2024, Saturday to Sunday and Thursday to Friday #TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice, R Degones and R Fuentes Accomplished: 1. Relocation of pole at Graceville, Barangay Tiza, Roxas City 2. Replacement of rotten pole at Sitio Marubrob, Barangay Parian, Sigma…
HUNYO 30, 2024 (Domingo nga adlaw) Alas 5:00 sang aga tubtob alas 7:00 sang aga Alas 4:00 sang hapon tubtob alas 6:00 sang hapon Ang NGCP temporaryo nga maga Shut Down sang Panitan Substation angot sa patigayunon nga Annual Preventive Maintenance Servicing Activities. Apektado nga Lugar: - BILOG NGA SEGUNDO…
June 27, 2024, Thursday Line clearing at Poblacion, Tapaz during the scheduled power interruption in the area Working Crew: #TeamMakiBitoon ML 1 Team Members: M Bitoon, R Durias, JJ Bereber and E Bithaos