CONSOLIDATED TEAM ACCOMPLISHMENT BT9

Published: July 22, 2024

July 17-20, 2024, Wednesday to Saturday

BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura and with K Cordovero and R Distura, Jr.
Accomplished:
1. Clearing of lines and payout of secondary lines at Barangay San Esteban, Pilar
2. Clearing of lines at Barangay Duran, Dumalag
3. Rehabilitation of metering at Sitio Bailan and Sitio Proper, Barangay Pinay. Mambusao
4. Relocation of pole at Barangay Anhawon, Panay
5.Replacement of rotten cross arm at Barangay Lus-onan, Panay (Done during the scheduled power interruption)