POST SCHEDULED POWER INTERRUPTION REPORT

Published: July 30, 2024

July 27, 2024, Saturday

As scheduled: From 5:00 AM to 6:00 AM
In Actual: From 5:07 AM to 5:54 AM
Reason: NGCP load normalization of CAPELCO President Roxas and transfer of Transformer 2 back to Panitan Substation
Areas Affected: Whole Municipality of Pilar, President Roxas, Maayon and portion of Panay, Pontevedra and Panitan
While power is out due to activities of the National Grid Corporation of the Philippines, CAPELCO personnel conducted hotspot correction at the Panitan Switchyard