CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7

Published: August 7, 2024

July 29-31 and August 3-4, 2024, Monday to Wednesday and Saturday and Sunday

BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes
Accomplished:
1. Installation of 1 unit of service old wood pole and rehabilitation of metering at Barangay Burias, Mambusao
2. Pull out of 50 KVA Transformer at Sitio Culasi, Barangay Lonoy, Sapi-an
3. Relocation of service pole and kilowatt hour meters at Barangay Matagnop, Dao
4. Hauling of 1 unit of pole to Barangay Ongol Ilawod, Dumarao
5. Relocation of pole and rehabilitation of kilowatt hour meters at Barangay Agnaga, Cuartero
6. Line upgrading and installation of 25 KVA transformer at Barangay Dolores, Dumalag (done during the scheduled power interruption)
7. Installation in of 37.5 KVA private transformer at Barangay Bunga, Mambusao
8. Replacement of rotten pole and uprating of transformer from 37.5 KVA to 50 KVA at Poblacion Ilaya, Panitan