CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

Published: August 29, 2024

August 12-16 and 19-22, 2024, Thursday to Tuesday and Friday to Monday

BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
Accomplished:
1. Relocation of pole and transfer Metering at brgy. Batabat Maayon Capiz
2. Installation of extension underbuilt line (paid project) at sitio Ilaya, Barangay Timpas, Panitan Capiz.
3. Replacement of 2 units of rotten Pole at Barangay San Roque, Dumalag
4. Installation of temporary 50 KVA transformer at Barangay San Roque, Tapaz
5. Relocation of metering at Barangay Parian, Sigma
6. Replacement of rotten pole at Barangay Mianay, Sigma
7. Replacement of damaged 37.5 KVA transformer at Barangay Pangabuan, Jamindan
8. Hauling of 35 ft pole at Jamindan area for replacement of damaged pole
9. Pull out of 3 units of 50 KVA rental transformer at Municipality of Panitan Public Plaza
10. Extension of 1-span primary line at Barangay Aglalana, Dumarao
11. Installation of 50 KVA transformer at Barangay Aglalana, Dumarao
12. Rehabilitation/transfer of kilowatt hour meters from old to new line and pull out idle materials at Barangay Dolores, Dumalag (one week stay-in at Dumalag Area Office)

Other News

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ“, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Sunday) Affected Areas: ๐Œ๐”๐๐ˆ๐‚๐ˆ๐๐€๐‹๐ˆ๐“๐˜ ๐Ž๐… ๐‰๐€๐Œ๐ˆ๐๐ƒ๐€๐ & ๐๐Ž๐‘๐“๐ˆ๐Ž๐ ๐Ž๐…...

read more

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’ , ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Saturday) Affected Areas: ๐๐”๐‘๐†๐Ž๐’ ๐ˆ๐‹๐€๐–๐Ž๐ƒ / ๐๐‹๐€๐™๐€ / ๐‘๐ˆ๐™๐€๐‹ / ๐“๐€๐๐๐”๐„ /...

read more

Follow Us

Other Related Posts