POST SCHEDULED POWER INTERRUPTION REPORT

Published: September 2, 2024

August 31, 2024, Saturday

As scheduled: From 5:00 AM to 7:00 AM and from 4:00 PM to 6:00 PM
In actual: From 5:46 AM to 6:49 AM and from 3:16 PM to 3:49 PM
Reason: The National Grid Corporation of the Philippines (NGCP) shall facilitate transfer of ILECO 3 Feeders to Panitan Sub-Station
Areas affected: Municipalities of Pilar, President Roxas, Maayon, portion of Pontevedra, portion of Panitan, most of Panay and barangays Adlawan, Liong, Loctugan, Bago and Olotayan, Roxas City
As scheduled: From 6:00 AM to 4:00 PM
In actual: From 6:10 AM to 2:15 PM
Reason: Transfer of lines affected by DPWH Road Widening Project and line clearing activity
BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes
BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes
BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas
ML 1 Team Members: M Bitoon, R Durias, JJ Bereber and E Bithao
ML 2 Team Members: L Acejo, E Dublado, R Delfin, J Escalada and N Estorque
ML 3 Team Members โ€“ K Cordovero and R Distura Jr
#NLBEnterprises โ€“ Line clearing contractor
As scheduled: From 5:00 AM to 1:00 PM
Accomplished: Line Clearing and Maintenance.
Affected areas: Barangays Capagao, Pasugue, Calaan, Panitan and Lacaron, Dao Line Section.