POST SCHEDULED POWER INTERRUPTION REPORT

Published: October 25, 2024

October 24, 2024, Thursday

As scheduled: From 8:30 AM to 5:00 PM
In actual: From 8:30 AM to 4:30 PM
Areas affected: 7-11 Jamindan, Jamindan Water System, Barangays Agambulong, San Vicente, Pangabat and Masgrau, Jamindan.
Accomplished: Line clearing operation, replacement of rotten poles and relocation of poles
Working crews:
BT 8 Team Members: R Distura, R Sombilla, JP Hachuela, J Arroyo and R Parohinog
BT 9 Team Members: H Delfin, RV Fadirugao, D Celoso Jr, A Daliva and F Distura
ML 1 Team Members โ€“ M Bitoon, R Durias, JJ Bereber and E Bithao
ML 2 Team Members: L Acejo, E Dublado, R Delfin, J Escalada and N Estorque
#NLBEnterprises – Line clearing contractor

Other News

Ang Presyo sang Kuryente sa Bulan sang Hunyo Nag Nubo!

๐Œ๐€๐€๐˜๐Ž ๐๐†๐€ ๐๐€๐‹๐ˆ๐“๐€! ๐€๐๐† ๐๐‘๐„๐’๐˜๐Ž ๐’๐€๐๐† ๐Š๐”๐‘๐˜๐„๐๐“๐„ ๐’๐€ ๐๐”๐‹๐€๐ ๐’๐€๐๐† ๐‡๐”๐๐˜๐Ž ๐๐€๐† ๐๐”๐๐Ž! Humalin Abril 2025,...

read more

Stay Connected with CAPELCO

๐’๐“๐€๐˜ ๐‚๐Ž๐๐๐„๐‚๐“๐„๐ƒ ๐–๐ˆ๐“๐‡ ๐‚๐€๐๐„๐‹๐‚๐Ž in this holiday season and pay your Electric Bills on or before due...

read more

Follow Us

Other Related Posts