ACCOMPLISHMENT REPORT

Published: January 20, 2025

January 15, 2025; (8:00 am to 4:30 pm)
Accomplished:
1.Line Clearing
2.Replacement of rotten poles @Brgy. Tmpas Panitan and Malapad, Cogon, Sigma (5poles)
3. Relocation of pole @Brgy Timpas, Panitan
4. Replacement of deffective insulator and short shunk steel pin to long shunk
Team: BT6, BT7, BT8, BT9, BT10,BT11,ML-1, ML-3 and NLB contractor