POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

As scheduled: From 8:30 AM to 5:00 PM In actual: From 8.30 AM to 3:45 PM Area Affected: Barangay Burias, Mambusao Accomplished: 1. Replacement of 3 units of rotten poles 2. Relocation of 2 units of poles 3. Replacement of polymer insulators 4. Line clearing operation...

read more
SCHEDULED POWER INTERRUPTION

SCHEDULED POWER INTERRUPTION

HULYO 9, 2024 (Martes nga adlaw) Alas 4:00 tubtob Alas 8:00 sang aga Ang National Grid Corporation of the Philippines o NGCP TEMPORARYO nga maga shut-down sang CAPELCO Feeders (69KV Panitan-Roxas Transmission Line kag Timpas Power Transformer 1) para mag patigayon...

read more
SCHEDULED POWER INTERRUPTION

SCHEDULED POWER INTERRUPTION

Alas 8:00 sang aga tubtob Alas 5:00 sang haponAng CAPELCO mapatigayon sang Line Clearing kag Maintenance1. HULYO 8, 2024 (Lunes ng adlaw)LUGAR NGA APEKTADO: Sitio Bughaan kag sitio Hacienda Tunga, Dulangan, Pilar2. HULYO 9, 2024 (Martes nga adlaw)LUGAR NGA APEKTADO:...

read more
POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

July 5, 2024, Friday, From 1:11 PM to 1:37 PM Estimated Duration as Planned: 1 hour and 30 minutes Actual Duration: 26 Minutes only Areas Affected: Feeder 3 – Portion of Maayon and Panitan Accomplished : Replaced broken pin and suspension insulators at Cadio Crossing...

read more
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11

Working Crew: #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella and M Deocampo Accomplished: 1. Rehabilitation of line and metering 2. Clearing of 3-phase lines beside of Villareal Stadium, Barangay Tiza, Roxas City 3. Correction and clearing of lines at Hortus...

read more