POST EMERGENCY POWER INTERRUPTION REPORT
8:53 pm to 9:39 pmCause:Toppled tree causing trip-off of Feeder F4Areas affected: Ivisan, portion of Sigma and Timpas, Panitan.CHRONOLOGY8:53 pm - Trip-off Feeder F49:02 pm - Restored Feeder F4 except Basiao, Ivisan9:39 pm - Feeder F4 totally...

POST EMERGENCY POWER INTERRUPTION REPORT
7:20 pm to 8:35 pm Cause: Disconnected three-phase line at Barangay Palaguian Maayon causing the tripping off of Feeder 3. Areas affected: Maayon, portion of Panitan and portion of Dao.

MEMBER-CONSUMER-OWNERS REQUEST ACTED
• Replacement of Pole at Barangay Tanza Sur, Panay • Relocation of pole at Poblacion Ilaya, Panay Working Crew: #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, J Degones, J Hachuela and M Deocampo

POST SCHEDULED POWER INTERRUPTION REPORT
From 8:00 AM to 4:30 PM Areas affected: Barangays Concepcion, San Roque, San Agustin, San Martin and portion of Sta. Teresa, Dumalag Accomplished: Relocation, conversion and clearing of lines Working Crews: #TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, J...

SCHEDULED POWER INTERRUPTION
HUNYO 22, 2024 (Sabado nga adlaw) Alas 5:00 tubtob 7:00 sang aga (2 Oras) Alas 5:00 tubtob 6:00 sang hapon (1 Oras) Ang National Grid Corporation of the Philippines o NGCP TEMPORARYO nga maga Shut Down sang ila 69KV Nabas-Sapian Line para mag patigayon sang Load...
Other News
SCHEDULED POWER INTERRUPTION
Alas 8:00 sang aga tubtob Alas 4:30 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag...
SCHEDULED POWER INTERRUPTION
HUNYO 30, 2024 (Domingo nga adlaw) Alas 5:00 sang aga tubtob alas 7:00 sang aga Alas 4:00 sang...
CONSOLIDATED TEAM ACCOMPLISHMENTS ML1
Line clearing at Poblacion, Tapaz during the scheduled power interruption in the area Working...
CONSOLIDATED TEAM ACCOMPLISHMENTS ML2
#TeamLarryAcejo ML 2 Team Members: L Acejo, E Dublado, R Delfin, J Escalada and N Estorque...
POST SCHEDULED EMERGENCY POWER INTERRUPTION REPORT
As scheduled: From 12:00 NN to 12:45 PM In actual: From 12:00 NN to 12:24 PM Areas affected: •...