POST EMERGENCY POWER INTERRUPTION ADVISORY
As scheduled: From 7:00 PM to 8:00 PM In actual: From 7:00 PM to 7:20 PM Purpose: Monitoring and Evaluation Areas affected: Municipalities of Dao, Cuartero, Dumarao, Dumalag and...

MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The secondary power cables and the 69KV post insulators are being installed. The activity is now being watched by NGCP represented by Engr. Cyril Aguilar who will also stay at the site to monitor the progress of the work, the results of the testing and the...

MEMBER-CONSUMER-OWNER REQUEST ACTED
San Jose Ville, Barangay San Jose Roxas City Rehabilitation of kilowatt hour meters Working Crew: #TeamCAPELCOTaskForce Isuzu 2 Team Members: M Nain, G Datar, E Delos Santos and E...

MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The installation of the ground cables is almost complete and parallel to the work is the interconnection of overhead cables. The SF6 circuit breaker is now ready for testing subject for the confirmation of the National Grid Corporation of the Philippines. CAPELCO...

MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The work at Dao Substation continue as the crew are now laying down the cables for the interconnection of the 15 MVA power transformer. This is 15 hours of straight work already in time for the eventual energization by tomorrow and the restoration of power for the...
Other News
POST EMERGENCY POWER INTERRUPTION REPORT
June 6-7, 2024, Various times, dates and areas Mambusao and Dumalag Area...
POST EMERGENCY POWER INTERRUPTION REPORT
The 20 MVA Power transformer at Lawaan Substation experienced multiple tripping at the height of...
BILLING RATE FOR JUNE 2024
SCHEDULED POWER INTERRUPTION
HUNYO 8, 2024 (Sabado nga adlaw)10:00 tubtob 11:00 sang agaAng CAPELCO maga conduct sang timing...
SCHEDULED POWER INTERRUPTION
8:00 sang aga tubtob 5:00 sang haponAng CAPELCO mapatigayon sang Line Clearing kag Maintenance.1....