POST EMERGENCY POWER INTERRUPTION REPORT
Areas affected: Whole Second District with the exception of the Municipality of Ivisan Cause: Tripping off of NGCP Panitan-Sapian Transmission line triggered by the Under Frequency Relay (UFR) because of multiple tripping of power plants at Negros Island. CAPELCO...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo Accoplished 1. Correction of pole leaning at Barangay Barra Roxas City 2. Pole dressing in preparation for the payout of conductor at Barangay Gabuan, Roxas...

CAPELCO ATTENDED THE SANGGUNIANG BAYAN COMMITTEE HEARING AT PRESIDENT ROXAS CAPIZ
Sangguniang Bayan Session Hall, President Roxas Capiz Acting General Manager Engr. Edgar D. Diaz and District III Director Mitchelle John B. Patricio represented in this hearing convened by the Sangguniang Bayan Committee on Public Utilities and facilities to shed...

SCHEDULED POWER INTERRUPTION
Ang CAPELCO maga matigayon sang Line Clearing kag Maintenance.1. HUNYO 13, 2024 (Huwebes nga adlaw)alas 8:30 sang aga tubtob alas 5:00 sang haponLUGAR NGA APEKTADO: Brgy. Agcabugao to San Antonio, Cuartero Line Section.2. HUNYO 14, 2024 (Biyernes nga adlaw)alas 8:00...

POST EMERGENCY POWER INTERRUPTION REPORT
Various Dates, Areas and Causes ROXAS CITY AREA OFFICE (June 10, 2024, Monday) From 7:31 PM to 8:05 PM and from 8:55 PM to 10:03 PM Areas affected: Opening of different phases in the 3-phase line Area affected: Barangay Milibili, Roxas City From 7:34 PM to 8:30 PM...
Other News
MEMBER-CONSUMER-OWNERS REQUEST ACTED
Accomplished: Re-tensioning of sagging secondary line Working Crew: #TeamPRAOBAPA,...
POST EMERGENCY POWER INTERRUPTION REPORT MAMBUSAO AREA OFFICE
Reason: Tripping off of Feeder M2 (Municipality of Mambusao) due to toppled pine tree into the...
EMERGENCY REPAIR AND POWER RESTORATION
From 7:14 PM to 8:38 PM Areas affected: Feeder L1 Municipality of Pilar Working Crew:...
PRE-EMPTIVE POWER INTERRUPTION
Time: Anytime soon Affected Areas: Municipality of Pilar Repair of three-phase line at San...
SCHEDULED POWER INTERRUPTION
1. HUNYO 24, 2024 (Lunes nga adlaw)Alas 8:00 sang aga tubtob 5:00 sang haponAng CAPELCO...