PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
Taking time that power is out due to the Preventive Maintenance Servicing of Dao Substation, CAPELCO’s construction crew and the maintenance crew of Dao Area Office conducted parallel activities to make use of the time that power is out. Accomplished: 1. Replacement...
CAPELCO OUTREACH AND INFORMATION EDUCATION CAMPAIGN (IEC) ON DISTRICT II (PONTEVEDRA AND MAAYON)
Mar Roxas Hall, Pontevedra, Capiz Director Emmanuel M. Oquendo has reached out to the Barangay Officials of the Municipality of Pontevedra as a way of conveying to them the recent updates on the operation of CAPELCO. Invited during the Liga Night, Director Oquendo was...
POST EMERGENCY POWER INTERRUPTION REPORT
From 4:11 AM to 8:58 AM Affected areas: Municipality of Sapian, Mambusao and Jamindan Chronology: • 4:11AM – Tripping off of 69 KV tapping point at Bangkal, Maninang affecting Sapian, Mambusao and Jamindan • 4:53 AM – Normalized all feeder lines • 5:50 AM – Tripping...
MEMBER-CONSUMER-OWNER REQUEST ACTED
Barangay Bula, Mambusao Accomplished: Relocation of pole Working Crew: #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog #TeamMAOMaintenance Team Members; E Taborda and L Llorente
PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
Taking time that power is out due to the Preventive Maintenance Servicing of Mambusao Substation and Tapping Point, CAPELCO’s construction crew and the maintenance crew of Mambusao Area Office conducted parallel activities to make use of the time that power is out....
Other News
BARANGAY POWER ASSOCIATION (BAPA) STRENGTHENING ACTIVITIES
Mambusao Area Office Manawayan BAPA, Maninang, Sapian Coordination meeting facilitated by MAO...
COMPOSITE TEAM ACCOMPLISHMENTS
Composite Team is made up of newly-graduated trainee lineworkers Jeep 5 Team Members: J Degones, S...
SCHEDULED POWER INTERRUPTION
ORAS: 8:00 sang aga tubtob 5:00 sang haponAng CAPELCO magapatigayon sang Line Maintenance kag...
JOINT TEAM ACCOMPLISHMENTS BT 11
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo Accomplished:...
SCHEDULED POWER INTERRUPTION
MAYO 24, 2024 (BIYERNES nga adlaw)Ang CAPELCO magapatigayon sang Scheduled Preventive Maintenance...