CONSOLIDATED TEAM ACCOMPLISHMENT BT9
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Installation of intermediate pole (mano-mano) at Barangay Traciano, Dumarao 2. Digging of pole at Sitio Bisyok, Barangay Traciano,...

MEMBER-CONSUMER-OWNER’S REQUEST ACTED
Sitio Baklayan. Barangay Mianay, Sigma Accomplished: Replacement of two (2) units of rotten pole and transfer kilowatt hour meters at Sitio Baklayan, Barangay Mianay, Sigma (FB Complaint) Working Team: #TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, J Penuela,...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT7
#TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes Accomplished: 1. Relocation of two (2) units of poles, transfer kilowatt hour meters, insertion of pole and clearing of line at Barangay Artuz, Tapaz 2. Replacement of rotten...

JOINT TEAM ACCOMPLISHMENTS BT8, BT9 AND ML1
This was during the scheduled interruption made for the purpose. Accomplished: 1. Relocation of pole and transfer Metering at Barangay West Villaflores, Maayon 2. Line clearing operation Working Crews: #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J...

PANITAN SUBSTATION SCADA OFFICIALLY POWERED UP
The Supervisory Control and Data Acquisition (SCADA) installed at Panitan Substation is now operational. The activation was done early morning today during the scheduled power interruption made for the purpose. The latest to be added into the SCADA System is Panitan...
Other News
CONSOLIDATED TEAM ACCOMPLISHMENTS ML2
#TeamArlanDangan ML 2 Team Members: A Dangan, E Dublado, R Delfin, J Escalada, N Estorque and L...
CONSOLIDATED TEAM ACCOMPLISHMENT BT9
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
#TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog...
POST EMERGENCY POWER INTERRUPTION REPORT
Reason: Emergency repair of damaged Blade Disconnection Switch caused by animal intrusion. Areas...
POST SCHEDULED POWER INTERRUPTION REPORT
From 8:30 AM to 5:00 PM Affected Areas: • Barangay Mangoso. Sitio Maralusan, Atiplo, Mambusao. •...