WEEKLY AND CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
#TeamGeraldCondino BT 8 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas Accomplished: 1. Complete grounding installation for 3-phase line at Pueblo de Panay, Lawaan to Dinginan, Roxas City 2. Pull-out of old pole and transfer of line to new erected...
SCHEDULED POWER INTERRUPTION
8:30 sang aga tubtob 4:30 sang haponAng CAPELCO mapatigayon sang Line Maintenance kag Clearing.1. MARSO 11, 2024 (Lunes nga adlaw)LUGAR NGA APEKTADO:-Brgy. Pasugue kag Cala-an Sur, Panitan-Brgy. Lacaron, Dao2. MARSO 12, 2024 (Martes nga adlaw)LUGAR NGA APEKTADO:-Brgy....
CONSOLIDATED TEAM ACCOMPLISHMENTS BT7
The crew are staying at Tapaz to maximize their accomplishments #TeamRamilDistura BT7 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Replacement of 3 units of capacitor at Barangay San Jose, Tapaz 2. Digging and erection of 5...
JOINT TEAM ACCOMPLISHMENTS BT1, BT2 AND BT7
Accomplished: Pull out of idle materials, transfer/rehabilitation of kilowatt hour meters and upgrading of transformer from 25 KVA to 37.5 KVA at Barangay Dangula, Dumarao Working crews: #TeamTamtamDangan BT1 Team Members: A Dangan, R Daliva, J Penuela, J Degones and...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 2
#TeamKennyCordovero BT2 Team Members: K Cordovero, A Ferrer and R Distura Accomplished: Continued correction of grounding for feeder D4 single phase line at Barangay Amaga, Sigma.
Other News
AREA OFFICE MAINTENANCE ACTIVITY
President Roxas Area Office Accomplished: Insertion of pole at Sitio Tinondojan, Barangay...
BARANGAY POWER ASSOCIATION (BAPA) STRENGTHENING ACTIVITIES
Mambusao Area Office Parian BAPA 2, Parian, Sigma Coordination meeting facilitated by MAO...
CONSOLIDATED TEAM ACCOMPLISHMENT BT11
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, M Batuampo and M Deocampo Accomplished:...
AREA OFFICE MAINTENANCE ACTIVITY
Dumalag Area Office Accomplished: Transfer of line and kilowatt hour meters to new pole at...
THIRD MONTHLY MEETING FOR 2024 OF MANAGERS, SUPERVISORS AND SECTION HEADS WITH ACTING GENERAL MANAGER
The meeting was to review key things that has to be done and to address the recurring concerns...