CONSOLIDATED TEAM ACCOMPLISHMENTS BT 9

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 9

#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura 1. Replacement of toppled 2 units rotten poles and rehabilitation of meters (mano-mano) at Barangay Cubi, Dumarao 2. Installation of 25 KVA private transformer at Camp...

read more
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7

#TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes Accomplished: 1. Installed additional 50 KVA transformer at Poblacion Ilaya, Dumarao 2. Uprating of transformer from 25 KVA to 37.5 KVA at Barangay Astorga,...

read more
TWO WEEKS OF CONSOLIDATED TEAM ACCOMPLISHMENTS BT 10

TWO WEEKS OF CONSOLIDATED TEAM ACCOMPLISHMENTS BT 10

#TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas Accomplished: 1. Continued rehabilitation of lines at Barangay Barra, Roxas City • Installation of 2 span o/s line • Transfer/rehabilitation of 20 kilowatt hour meters 2....

read more
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

Accomplished: Replacement of damaged polymer insulators and line clearing operation From 5:45 AM to 2:26 PM Areas Affected: Barangay New Guia, Old Guia, Carataya, Jebaca, Cabungahan and Balighot, Maayon From 5:45 AM to 9:18 AM Areas Affected: Agloway, Enseñagan and...

read more
MEMBER-CONSUMER-OWNER REQUEST ACTED

MEMBER-CONSUMER-OWNER REQUEST ACTED

Pandayan BAPA, Concepcion, Dumalag Accomplished: Replacement of leaning pole Working Crew: #TeamDUMAOMaintenance Team Members: J Fedalgo, A Francisquite, H Egido and N Facinal

read more