POST EMERGENCY POWER INTERRUPTION REPORT
September 24, 2024, Tuesday From 7:15 PM to 10:00 PM Reason: Disconnected jumper due to broken insulator due to intrusion of gecko into the distribution line Actions taken: Replacement of broken insulator, replacement of power fuse and reconnection of jumpers Areas...

POST EMERGENCY POWER INTERRUPTION REPORT
September 24, 2024, From 8:21 PM to 8:44 PM Reason: Tripping off of NGCP Panitan-Sara 69 kV Transmission Line triggered by Under Frequency Relay (UFR) Switch. Areas Affected: FEEDER 1 (Municipality of Panay, portion of Panitan and Barangays Adlawan, Liong, Loctugan,...

EMERGENCY POWER INTERRUPTION
September 24, 2024, Tuesday President Roxas Substation is currently experiencing trouble due to disconnected jumpers of L2 and L3 Feeder lines. Without power as of the moment is the Municipality of Pilar, President Roxas, portion of Pontevedra and upland Maayon. Our...

SCHEDULED POWER INTERRUPTION
Septembre 26, 2024 (Huwebes nga adlaw)Alas 8:30 sang aga tubtob 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag MaintenanceLugar nga Apektado:-Sitio Gapason, Brgy. Nasunogan & Agtambi, Dao.-Brgy. San Agustin, San Martin kag portion sang Brgy. San...

CONSOLIDATED TEAM ACCOMPLISHMENTS ML2
September 21 and 23, 2024, Saturday and Monday #TeamLarryAcejo ML 2 Team Members: L Acejo, E Dublado, R Delfin, J Escalada and N Estorque Accomplished: 1. Line clearing from Rizal and to Basiao, Ivisan 2. Line clearing from Barangay Cogon, Panay to Sublangon,...
Other News
CONTINUOUS ROLL-OUT OF THE SEMA PROJECT
October 3, 2024, Thursday Barangay Cabugao, Roxas City Of the 45 applicants from Barangay Cabugao,...
FIRST CONSOLIDATED BANK (FCB) MAMBUSAO BRANCH NOW ACCEPTING PAYMENT OF ELECTRIC BILLS!
The payment shall be accepted by FCB provided… Current month bill With "current" account and...
SCHEDULED POWER INTERRUPTION
Oktubre 5, 2024 (Sabado nga adlaw)Alas 6:00 tubtob alas 10:00 sang agaAng CAPELCO magapatigayon...
EMERGENCY POWER INTERRUPTION
October 3, 2024, Thursday Around 11:10 am Cause: Recloser Jumper cut-off Areas Affected: Feeder L1...
EMERGENCY POWER INTERRUPTION
October 3, 2024, Thursday Reason: Emergency replacement of insulator at Mckinley Street, Roxas...