CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7
July 21-24 and July 26-28, 2024, Sunday to Wednesday and Friday to Sunday #TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes Accomplished: 1. Installation of intermediate pole, Relocation of pole, Replacement of rotten pole...

CONSOLIDATED TEAM ACCOMPLISHMENT BT9
July 23-27, 2024, Tuesday to Saturday #TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Relocation and insertion of intermediate pole (mano2x) at Sitio Pangpang Barangay Balucuan, Sigma (FB Complain) 2....

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
July 22-26, 2024, Monday #TeamRamilDistura to FridayBT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Replacement of 3 units of disconnect switch to cutout at Barangay Bungsuan, Dumarao 2. Replacement of rotten pole at...

SIXTH MONTHLY MEETING FOR 2024 OF MANAGERS, SUPERVISORS AND SECTION HEADS WITH ACTING GENERAL MANAGER
July 29, 2024, Monday Apart from the agenda scheduled for the meeting, Acting General Manager Engr. Edgar D. Diaz reported that CAPELCO was invited by the Municipality of Tapaz relative to concerns on power services in the municipality. He explained that it was an...

BARANGAY POWER ASSOCIATION (BAPA) STRENGTHENING ACTIVITIES
Dumalag Area Office July 26, 2024, Friday Consolacion BAPA, Consolacion, Dumalag Coordination meeting facilitated by Director Manuel F. Farenas and DUMAO personnel Ranilo B. Balle and Miriam Alingao
Other News
SCHEDULED POWER INTERRUPTION
AGOSTO 9, 2024 (Biyernes nga adlaw)Alas 6:00 tubtob Alas 7:30 sang aga.Ang CAPELCO magapatigayon...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
July 29 to August 2, 2024, Monday to Friday #TeamRamilDistura BT8 Team Members: R Distura, R...
MONTH LONG CONSOLIDATED TEAM ACCOMPLISHMENTS BT10
July 1 - 30, 2024, Whole month of July 2024 #TeamGeraldCondino BT 10 Team Members: G Condino, C...
POST SCHEDULED POWER INTERRUPTION REPORT
August 6, 2024, Tuesday As scheduled: From 6:00 AM to 7:00 AM In actual: From 6:01 AM to 6:30 AM...
SCHEDULED POWER INTERRUPTION
AGOSTO 6, 2024 (Martes nga adlaw)Alas 6:00 tubtob Alas 7:00 sang aga.Ang CAPELCO magapatigayon...