POST SCHEDULED POWER INTERRUPTION REPORT
As scheduled: From 8:30 AM to 5:00 pm In actual: From 8:30 AM to 4:30 PM Areas affected: Barangays Balighot, Cabungahan, Jebacca, Carataya, New Guia and Old Guia, Maayon Accomplished: 1. Relocation of 2 units of poles (2 units) and rehabilitation of kilowatt hour...
SCHEDULED POWER INTERRUPTION
HUNYO 28, 2024 (Biyernes nga adlaw)Alas 8:00 sang aga tubtob alas 5:00 sang haponAng CAPELCO magapatigayon sang Clearing kag Line Maintenance.Apektado nga Lugar: sitio Rosario, Brgy. Lantangan kag sitio Caringala, Brgy. Jolongajog, Pontevedra.Gilayon man nga ibalik...
POST EMERGENCY POWER INTERRUPTION REPORT
ROXAS CITY AREA OFFICE June 25, 2024, from 9:04 PM to 10:15 PM Areas affected: Barangay Lus-onan ang Linao, Panay Reason: Damaged polymer insulator at Lus-onan, Panay Responding Crew: #TeamRCAOMaintenance Team Members: J Avaricio and I Dais June 26, 2024, from 11:25...
SCHEDULED POWER INTERRUPTION
HUNYO 27, 2024 (Huwebes nga adlaw) Alas 5:00 tubtob alas 6:00 sang aga Ang CAPELCO magapatigayon sang EMERGENCY Repair sang nasamad ng Crossarm sa Baybay, Roxas City. Apektado nga Lugar: (FEEDER B2) Barangay Baybay pakadto sa Barangay Culasi kalakip ang porsyon sang...
SCHEDULED POWER INTERRUPTION
HUNYO 27, 2024 (Huwebes nga adlaw) Ang CAPELCO magapatigayon sang Line Maintenance kag Clearing. 1. Alas 6:00 sang aga tubtob 12:00 sang udto Apektado nga Lugar: halin Crossing Switch to Poblacion, Tapaz. 2. Alas 6:00 sang aga tubtob alas 5:00 sang hapon. Apektado nga...
Other News
SCHEDULED POWER INTERRUPTION
Alas 8:00 sang aga tubtob Alas 4:30 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag...
SCHEDULED POWER INTERRUPTION
HUNYO 30, 2024 (Domingo nga adlaw) Alas 5:00 sang aga tubtob alas 7:00 sang aga Alas 4:00 sang...
CONSOLIDATED TEAM ACCOMPLISHMENTS ML1
Line clearing at Poblacion, Tapaz during the scheduled power interruption in the area Working...
CONSOLIDATED TEAM ACCOMPLISHMENTS ML2
#TeamLarryAcejo ML 2 Team Members: L Acejo, E Dublado, R Delfin, J Escalada and N Estorque...
POST SCHEDULED EMERGENCY POWER INTERRUPTION REPORT
As scheduled: From 12:00 NN to 12:45 PM In actual: From 12:00 NN to 12:24 PM Areas affected: •...