SCHEDULED POWER INTERRUPTION
AGOSTO 10, 2024 (Sabado nga adlaw)Alas 6:00 sang aga tubtob Alas 2:00 sang hapon.Ang CAPELCO magapatigayon sang Rephasing sang linya halin sa Single Phase pakadto sa Three Phase Line.LUGAR NGA APEKTADO:Hemingway St., Atienza St. Back kag porsyon sang DPWH, Roxas...

SCHEDULED POWER INTERRUPTION
AGOSTO 9, 2024 (Biyernes nga adlaw)Alas 6:00 tubtob Alas 7:30 sang aga.Ang CAPELCO magapatigayon sang Installation sang Intermediate Pole sa Plaridel St., Roxas CityLUGAR NGA APEKTADO:- CAPSU Main- St. Anthony Hospital- Nestas Hill Top- Gaisano Market- TATCGilayon man...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
July 29 to August 2, 2024, Monday to Friday #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Replacement of rotten pole at Barangay Poblacion Sur, Sigma 2. Replacement of rotten pole at Barangay Bita, Dao 3....

MONTH LONG CONSOLIDATED TEAM ACCOMPLISHMENTS BT10
July 1 - 30, 2024, Whole month of July 2024 #TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas Accomplished: 1. Replacement of damage 50 KVA transformer at Sitio Tagudtod, Poblacion, Ivisan 2. Installation of groundings at...

POST SCHEDULED POWER INTERRUPTION REPORT
August 6, 2024, Tuesday As scheduled: From 6:00 AM to 7:00 AM In actual: From 6:01 AM to 6:30 AM Reason: Emergency Hotspot Correction. Areas affected: • Municipality of President Roxas • Portion of the Municipality of Pontevedra especially the coastal barangays and...
Other News
ROXAS CITY AREA OFFICE SATURDAY PAYMENT SCHEDULE
POST SCHEDULED EMERGENCY POWER INTERRUPTION REPORT
August 13, 2024, Tuesday As scheduled: From 12:30 PM to 12:45 PM In actual: From 12:00 PM to 12:11...
MOBILIZING COMMUNITY SUPPORT FOR LINE CLEARING OPERATION
August 9 and August 12, 2024, Friday and Monday Barangay Milibili and Barangay Talon, Roxas City...
CAPELCO JOINED HINUN-ANON SA BARANGAY
August 9, 2024, Friday Barangays Caridad, Lapaz and Bo. Fe, Jamindan CAPELCO joined the Philippine...
POST EMERGENCY POWER INTERRUPTION REPORT
August 13, 2024, Tuesday, From 10:55 AM to 11:36 AM Tripping off of 69KV transmission line at...