CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

July 22-26, 2024, Monday #TeamRamilDistura  to FridayBT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Replacement of 3 units of disconnect switch to cutout at Barangay Bungsuan, Dumarao 2. Replacement of rotten pole at...

read more
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

July 27, 2024, Saturday As scheduled: From 8:00 AM to 4:00 PM In actual: From 8:00 AM to 3:35 PM Reason: Pole relocation affected by DPWH Road Widening Project Affected areas: Portion of Barangay Bailan, Barangays Ilawod, Ilaya, Tabuc, Tacas, Malag-it, Agbanog,...

read more