(0963) 043 8339 info@capelco.com
POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

May 19-20, 2024, Sunday to Monday MAMBUSAO AREA OFFICE May 19, 2024 From 3:53 PM to 8:45 PM Affective areas: Pasol-o, Milan. Lucero, Igang, San Juan and Ganzon Cause: Toppled Bamboo tree into the distribution line at Pasol-o, Jamindan From 4:00 PM to 9:00 PM Electric...
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

May 19, 2024, Sunday May 19, 2024, SundayChronology of Time and Areas affected:As scheduled: From 5:00 AM to 4:00 PMIn actual: From 5:05 AM to 2:25 PMReason: Conduct of Annual Preventive Maintenance Services (PMS) for Lawaan Substation.Areas affected:• FEEDER 1R-...