ACCOMPLISHMENT REPORT

ACCOMPLISHMENT REPORT

March 1, 2025 (Saturday) SUCCESSFUL REPLACEMENT OF POLE, CROSS-ARM, INSULATORS, & CORRECTION & CLEARING OF LINES Scheduled time to complete: 6:00AM-12:00NN Actual time of completion: 6:00AM-10:27AM The Technical Teams behind the successful operation and early...
EMERGENCY POWER INTERRUPTION

EMERGENCY POWER INTERRUPTION

February 28, 2025, Friday 4:00 pm to 4:30 pm CAPELCO will conduct EMERGENCY Hotspot Correction of Panitan Transformer 1. Affected Areas: Feeder 2: -Municipality of Pontevedra -Portion Brgys. of Panitan -Portion Brgys. of Panay Feeder 4: – Portion of Brgy....
SCHEDULED POWER INTERRUPTION

SCHEDULED POWER INTERRUPTION

Alas 8:00 sang aga tubtob alas 4:30 sang haponAng CAPELCO magapatigayon sang Line Clearing kag Maintenance.1. MARSO 4, 2025 (Martes nga adlaw)Lugar nga Apektado: Brgy. Taslan kag Traciano, Dumarao.2. MARSO 5, 2025 (Miyerkules nga adlaw)Lugar nga Apektado: Crossing...
CAPELCO, Kiwanis, and Red Cross Team Up for Blood Letting Activity

CAPELCO, Kiwanis, and Red Cross Team Up for Blood Letting Activity

A meeting held yesterday at the CAPELCO Roxas City Office to finalize preparations for the upcoming bloodletting activity, a joint project of CAPELCO, Kiwanis Division 2-B, and the Red Cross Capiz Chapter. The bloodletting activity is scheduled to take place on 𝗠𝗮𝗿𝗰𝗵...
EMERGENCY POWER INTERRUPTION

POST EMERGENCY POWER INTERRUPTION REPORT

February 24, 2025, Monday Power Out: 9:39 am Power Restored: 9:57 am However, 3 phase line going San Juan, Baybay and Culasi, has no power due to a damaged pole top pin at San Juan, Baybay (near Tabai) Power Normalized: 10:40 am...