EMERGENCY POWER INTERRUPTION

EMERGENCY POWER INTERRUPTION

October 14, 2024, Monday CAPELCO will undergo Emergency Correction of Line due to a Broken Primary Line. Areas Affected: Crossing Patag, Lawaan to Brgy. Dinginan, Roxas City Estimated Time: 1...
POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

October 12-13, 2024, Saturday to Sunday From 11:22 PM to 11:28 PM Tripping off of Panitan-Roxas NGCP Transmission Line Areas affected: Whole of Roxas City with the exception of Adlawan, Liong, Loctugan, Bago and Olotayan From October 12, 2024 at 11:22 PM to October...
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

October 12, 2024, Saturday As scheduled: From 6:00 AM to 3:00 PM In actual: From 6:00 AM to 2:55 PM Areas affected: Feeder D2 – Municipality of Dumalag and Tapaz Accomplished: Energization of new 3-phase line affected by DPWH Road Widening Project and line clearing...
POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

October 12, 2024, Saturday, From 9:46 AM to 10:00 AM Reason: Tripping off of Feeder B2 due to damaged pole top pin in front of San Antonio Report, Barangay Baybay, Roxas City Areas affected: From City Mall to Baybay and Culasi Line Section Responding Crew:...