CONSOLIDATED TEAM ACCOMPLISHMENTS BT 9
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Replacement of rotten pole and rehabilitation of metering at Barangay Timpas, Panitan ( FB complain) 2. Replacement of rotten pole at Barangay Conciencia,...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
#TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Dressing of 45 ft pole at Barangay Angub, Cuartero 2. Continue digging and installation of 2 units of 45ft pole at Barangay Sto. Angel, Dumalag 3. Hauling of...
SCHEDULED POWER INTERRUPTION
HUNYO 1, 2024 (Sabado nga adlaw) ORAS: 5:00 sang aga tubtob 6:00 sang hapon Ang National Grid Corporation of the Philippines ukon NGCP magapatigayon sang pag ilis sang mga Wood Pole sa 69KVA Panitan-Sara Line Section LUGAR NGA APEKTADO: Feeder L1, L2 kag L3 - Banwa...
MEMBER-CONSUMER-OWNER REQUEST ACTED
Sitio Bacurungan, Barangay Dacuton, Dumarao Installation of service pole and additional 25 KVA Transformer to address low voltage problem Working Crew: #TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F...
BRIGADA ESKWELA 2024
Accomplished: Clearing and upgrading of lines at Capiz National High School Gym Responding CAPELCO Personnel: IDSSD Manager Engr. Jovencio A. Villagracia, Engr. Ray Anthony Doloso, Lineman Paolo Agustin Bolinas and Irvin...
Other News
MEMBER-CONSUMER-OWNER REQUEST ACTED
San Jose Ville, Barangay San Jose Roxas City Rehabilitation of kilowatt hour meters Working Crew:...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The installation of the ground cables is almost complete and parallel to the work is the...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The work at Dao Substation continue as the crew are now laying down the cables for the...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The New 15 MVA Power transformer has been properly positioned into its mounting platform and the...
PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION
Making use that power is out at Dao Substation, the construction crew conducted their own...