POST SCHEDULED EMERGENCY POWER INTERRUPTION REPORT
As scheduled: From 12:00 NN to 12:45 PM In actual: From 12:00 NN to 12:24 PM Areas affected: • Feeder 2 – Municipality of Pontevedra (except those those connected at President Roxas Substation), portion of Panay and portion of Panitan • Feeder 4 – portion of Panitan,...

EMERGENCY SCHEDULED POWER INTERRUPTION
HUNYO 28, 2024 (Biyernes nga adlaw) Alas 12:00 sang udto tubtob alas 12:45 sang hapon Ang CAPELCO magapatigayon sang Hotspot Correction sang Loose Bolt sa Blade Disconnect Switch sa Panitan Sub Station. Apektado nga Lugar: FEEDER 2 - Banwa sang Pontevedra (magluwas...

POST EMERGENCY POWER INTERRUPTION REPORT
Reason: Tripping off of Feeder 4R due to disconnected primary jumper of the three-phase line in front of Edgen Bakeshop, Banica Roxas City Areas affected: Feeder 4R – Barangay Banica, Tanza, Bato, Mongpong, Culajao, Gabuan, Dumulog, Cogon, Punta Cogon and portion of...

MEMBER-CONSUMER-OWNERS REQUEST ACTED
West Lake Subdivision, Dayao, Roxas City Accomplished: Line clearing Working Crew: #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, J Degones, J Hachuela and M Deocampo Barangay Initan, Tapaz Accomplished: Relocation of pole Working Crew: #TeamHonepherDelfin...

FIFTH MONTHLY MEETING FOR 2024 OF MANAGERS, SUPERVISORS AND SECTION HEADS WITH ACTING GENERAL MANAGER
The meeting treshed out the emerging problems brought about by the sudden change of weather where widespread power service interruption is being experienced in different areas in Capiz. Tapaz and Dumarao in particular, are areas where power interruption is frequently...
Other News
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
#TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog...
RECOGNITION OF AN HONEST SECURITY GUARD
A special recognition was presented to SG Mark Clavero for his honesty while performing his job at...
FIRST FRIDAY MASS AND 7TH AGM MONTHLY MEETING
Rev. Fr. Edcel Delfin who officiated the traditional First Friday Mass articulated the message of...
CONSOLIDATED TEAM ACCOMPLISHMENT BT9
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura...
POST SCHEDULED POWER INTERRUPTION REPORT
As scheduled: From 8:30 AM to 5:00 PM In actual: From 8.30 AM to 3:45 PM Area Affected: Barangay...