CAPELCO CONGRATULATES JAGNAYA BAPA ON ITS 36TH ANNUAL GENERAL MEMBERSHIP ASSEMBLY
Jagnaya BAPA did it again! This Barangay Power Association has consistently demonstrated that exemplary leadership and dynamic membership are the formula to achieve success for any community-based association. Jagnaya BAPA is a success story and a best practice model...

PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
Taking time that power is out due to the Preventive Maintenance Servicing of Lawaan Substation, CAPELCO’s construction crew and the maintenance crew conducted parallel activities to make use of the time that power is out. Accomplished: 1. Replacement of crossarm at...

POST SCHEDULED POWER INTERRUPTION REPORT
May 19, 2024, SundayChronology of Time and Areas affected:As scheduled: From 5:00 AM to 4:00 PMIn actual: From 5:05 AM to 2:25 PMReason: Conduct of Annual Preventive Maintenance Services (PMS) for Lawaan Substation.Areas affected:• FEEDER 1R- Roxas Avenue, Punta...

POST SCHEDULED POWER INTERRUPTION REPORT
Areas affected: Feeder 4 – Municipality of Sigma and portion of the Municipality of Panitan As scheduled: From 5:00 AM to 8:00 AM In actual: From 5:05 AM to 9:04 AM Cause of the delay: Shattered insulator at the Blade Disconnect Switch at Crossing Andaya, Mianay,...

POST SCHEDULED POWER INTERRUPTION REPORT
Purpose: Hotspot Correction and Preventive Maintenance Servicing of the National Grid Corporation of the Philippines Chronology of Time and Areas affected: From 5:05 AM to 8:02 AM Areas connected at Panitan Substation • FEEDER 2 – Municipality of Pontevedra (except...
Other News
CONSOLIDATED POST SCHEDULED POWER INTERRUPTION REPORT
Line maintenance and line clearing at the Municipality of Cuartero and Dumarao and various work...
MEMBER-CONSUMER-OWNER REQUEST ACTED
Barangay Ilamnay, PanayAccomplished: Installation of intermediate poleWorking...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT6
#TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes Accomplished: 1....
POST EMERGENCY POWER INTRRUPTION REPORT
The sudden change in the weather has resulted to multiple cases of emergency power interruptions...
PARALLEL TECHNICAL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
Taking time that power is out due to the Preventive Maintenance Servicing of Panitan Substation,...