MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The secondary power cables and the 69KV post insulators are being installed. The activity is now being watched by NGCP represented by Engr. Cyril Aguilar who will also stay at the site to monitor the progress of the work, the results of the testing and the...
MEMBER-CONSUMER-OWNER REQUEST ACTED
San Jose Ville, Barangay San Jose Roxas City Rehabilitation of kilowatt hour meters Working Crew: #TeamCAPELCOTaskForce Isuzu 2 Team Members: M Nain, G Datar, E Delos Santos and E...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The installation of the ground cables is almost complete and parallel to the work is the interconnection of overhead cables. The SF6 circuit breaker is now ready for testing subject for the confirmation of the National Grid Corporation of the Philippines. CAPELCO...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The work at Dao Substation continue as the crew are now laying down the cables for the interconnection of the 15 MVA power transformer. This is 15 hours of straight work already in time for the eventual energization by tomorrow and the restoration of power for the...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The New 15 MVA Power transformer has been properly positioned into its mounting platform and the area has been cleared of debris. Initial testing has been made and the result is positive. Working crews are now preparing the interconnections of its cable and all other...
Other News
AREA OFFICE MAINTENANCE ACTIVITY
Mambusao Area Office Responding Team: #TeamMAOMaintenance Team Members: J Lacorte, R Marquez and...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7
#TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes...
POST EMERGENCY POWER INTERRUPTION REPORT
Report received 4:57 PM, Power restored 8:44 PM Areas affected: Most of Tapaz area Cause:...
PARALLEL ACTIVITIES DURING THE PREVENTIVE MAINTENANCE SERVICING OF BURGOS SUBSTATION
Accomplished: 1. Replacement of Steel Pole to Wood Pole at Burgos Substation 2. Transfer of...
POST SCHEDULED POWER INTERRUPTION REPORT
As scheduled: from 5:00 AM to 2:00 PM In actual: From 5:05 AM to 1:45 PM Reason: Preventive...