SCHEDULED POWER INTERRUPTION

SCHEDULED POWER INTERRUPTION

Ang CAPELCO magapatigayon sang Line Maintenance kag Clearing.1. ORAS: 8:30 sang aga tubtob 5:00 sang haponLUGAR NGA APEKTADO: Brgy. San Miguel (utod), Dumalag2. ORAS: 8:00 sang aga tubtob 5:00 sang haponLUGAR NGA APEKTADO: Brgy. Nagba to San Antonio, Cuartero Line...

read more
PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION

PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION

Taking time that power is out due to the Preventive Maintenance Servicing of Lawaan Substation, CAPELCO’s construction crew and the maintenance crew conducted parallel activities to make use of the time that power is out. Accomplished: 1. Replacement of crossarm at...

read more
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

May 19, 2024, SundayChronology of Time and Areas affected:As scheduled: From 5:00 AM to 4:00 PMIn actual: From 5:05 AM to 2:25 PMReason: Conduct of Annual Preventive Maintenance Services (PMS) for Lawaan Substation.Areas affected:• FEEDER 1R- Roxas Avenue, Punta...

read more
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

Areas affected: Feeder 4 – Municipality of Sigma and portion of the Municipality of Panitan As scheduled: From 5:00 AM to 8:00 AM In actual: From 5:05 AM to 9:04 AM Cause of the delay: Shattered insulator at the Blade Disconnect Switch at Crossing Andaya, Mianay,...

read more

Other News

Follow Us