CONSOLIDATED POST SCHEDULED POWER INTERRUPTION REPORT
Line maintenance and line clearing at the Municipality of Cuartero and Dumarao and various work during the preventive maintenance servicing of Panitan Substation Transformer 1.

MEMBER-CONSUMER-OWNER REQUEST ACTED
Barangay Ilamnay, PanayAccomplished: Installation of intermediate poleWorking Crew:#TeamRonaldDiliBT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes

CONSOLIDATED TEAM ACCOMPLISHMENTS BT6
#TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes Accomplished: 1. Relocation of pole at Barangay Cagay, Roxas City (DITO paid project) 2. Pull out of 37.5 KVA transformer at Arcabalo Milibili and installation of 37.5 KVA Transformer at...

POST EMERGENCY POWER INTRRUPTION REPORT
The sudden change in the weather has resulted to multiple cases of emergency power interruptions all over Capiz. These incidents reported in here are just a few of it and there are still areas experiencing emergency power interruption as of the moment. ROXAS CITY AREA...

PARALLEL TECHNICAL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
Taking time that power is out due to the Preventive Maintenance Servicing of Panitan Substation, CAPELCO’s construction crew and the maintenance crew conducted parallel activities to make use of the time that power is out. Accomplished: 1. Replacement of rotten pole...
Other News
PREPARATORY ACTIVITY FOR THE ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
Accomplished: 1. Installation of 1 span 3phase line @ Dao substation to energize Dao from Feeder 4...
POST SCHEDULED POWER INTERRUPTION REPORT
Reason: The National Grid Corporation od the Philippines (NGCP) will facilitate the replacement of...
LOW VOLTAGE ALERT ANGUT SA GINAPATIGAYON NGA PAGKAMBYO SANG POWER TRANSFORMER SA DAO SUBSTATION
Ang ginapatigayon nga pagbaylo sang 10 MVA nga Power Transformer sang bag-o nga 15 MVA Power...
TOOLBOX MEETING WITH NGCP, CONTRACTOR AND CAPELCO ENGINEERS
Agenda: Sequence of activities prior to the moving, installing and energization of 15 MVA power...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo Accomplished:...