AREA OFFICE MAINTENANCE ACTIVITY
Mambusao Area Office (MAO) #TeamMAOMaintenance Team: J. Adio, J. Lacorte and NJ Miguel Accomplished: Replacement of 2 units of rotten poles at Sitio Malonoy, Barangay Agambulong, Jamindan
CONSOLIDATED POST SCHEDULED POWER INTERRUPTION REPORT
Line maintenance and line clearing at the Municipality of Cuartero and Dumarao and various work during the preventive maintenance servicing of Panitan Substation Transformer 1.
MEMBER-CONSUMER-OWNER REQUEST ACTED
Barangay Ilamnay, PanayAccomplished: Installation of intermediate poleWorking Crew:#TeamRonaldDiliBT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes
CONSOLIDATED TEAM ACCOMPLISHMENTS BT6
#TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes Accomplished: 1. Relocation of pole at Barangay Cagay, Roxas City (DITO paid project) 2. Pull out of 37.5 KVA transformer at Arcabalo Milibili and installation of 37.5 KVA Transformer at...
POST EMERGENCY POWER INTRRUPTION REPORT
The sudden change in the weather has resulted to multiple cases of emergency power interruptions all over Capiz. These incidents reported in here are just a few of it and there are still areas experiencing emergency power interruption as of the moment. ROXAS CITY AREA...
Other News
EMERGENCY POWER INTERRUPTION
There is emergency repair that has to be done at Lawaan Subtstation which caused the initial...
POST EMERGENCY POWER INTERRUPTION ADVISORY
As scheduled: From 7:00 PM to 8:00 PM In actual: From 7:00 PM to 7:20 PM Purpose: Monitoring and...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The secondary power cables and the 69KV post insulators are being installed. The activity is now...
MEMBER-CONSUMER-OWNER REQUEST ACTED
San Jose Ville, Barangay San Jose Roxas City Rehabilitation of kilowatt hour meters Working Crew:...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The installation of the ground cables is almost complete and parallel to the work is the...