CONSOLIDATED TEAM ACCOMPLISHMENT BT9
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Replacement of 5 units of rotten poles and relocation of secondary lines at Barangay Cabangahan, Panitan 2. Replacement of rotten pole (mano-mano) at...
MEMBER-CONSUMER-OWNER’S REQUEST ACTED
Sitio Hawili, Quinat-uyan, MaayonAccomplished: Replacement of rotten poleWorking Team: #TeamTamtamDanganBT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
CONSOLIDATED TEAM ACCOMPLISHMENTS BT7
#TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes Accomplished: 1. Replacement of 2 units of rotten poles and transfer of kilowatt hour meter at Barangay Mahunod-hunod, Cuartero 2. Replacement of rotten pole and transfer of...
SCHEDULED POWER INTERRUPTION
Halin Alas 8:30 sang aga tubtob alas 4:30 sang haponRason: Ang CAPELCO magapatigayon sang Line Clearing lag Line MaintenanceLugar nga Apektado: Brgy. Pasugue kag Capagao, Panitan.
ONSITE PROCESSING OF APPLICATIONS OF RIZAL STREET FIRE VICTIMS
As a way to make processing of application for electric service connection, a team of CAPELCO personnel conducted onsite processing of application at Tanza Ville, Roxas City. These beneficiaries were the fire victims at Rizal Street who were relocated and provide...
Other News
AREA OFFICE MAINTENANCE ACTIVITY
Dao Area Office Accomplished: Pull out of old pole, transfer of metering to new line and...
POST EMERGENCY POWER INTERRUPTION REPORT
Areas affected: barangay Cubi, Bayog and Apipaciawan, Dumarao Cause: Toppled two (2) units of...
MEMBER-CONSUMER-OWNER REQUEST ACTED
Poblacion Ilaya, DumaraoAccomplished: Additional transformer to address low voltage problemWorking...
SCHEDULED POWER INTERRUPTION
MAYO 3, 2024 (Biyernes nga adlaw)8:30 sang aga tubtob 5:00 sang haponAng CAPELCO magapatigayon...
MEMBER-CONSUMER-OWNER REQUEST ACTED
Sitio Tacay, Astorga, Dumarao Accomplished: Additional transformer to address low voltage problem...