SCHEDULED POWER INTERRUPTION
Septembre 20, 2024 (Biyerbes nga adlaw)Alas 8:00 sang aga tubtob 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag Maintenance.Apektado nga Lugar: Porsyon sang Brgy. Batabat, West Villaflores kag East Villaflores, Maayon.Gilayon man nga ibalik ang...
POST SCHEDULED POWER INTERRUPTION REPORT
September 18, 2024, Wednesday As acheduled: From 5:00 AM to 7:00 AM In Actual: From 5:00 AM to 6:30 AM Areas affected: Whole Feeder 4R - San Roque Extension, New Fus, Mercedez Hotel, Sky Garden Hoel, Portion of Mckinley St., Portion of Magallanes St., Aguinaldo St.,...
POST EMERGENCY POWER INTERRUPTION REPORT
September 17, 2024, Tuesday From 10:07 AM to 12:39 PM Emergency tripping off of B2 Feederline Reason: Rotten Cross Arm at San Antonio Village, Baybay, Roxas City Working crew: #TeamRCAOMaintenance Team members; P Declaro, J Bautista Jr., F Buday and C...
SCHEDULED POWER INTERRUPTION
Ang CAPELCO magapatigayon sang Line Clearing kag Maintenance.1. Septembre 18, 2024 (Miyerkules nga adlaw)Alas 8:00 sang aga tubtob 5:00 sang hapon.Apektado nga Lugar: Sitio Baho, Brgy. Nasunugan, Dao kag portion sang Brgy. Quinabcaban, Dao.2. Septembre 19, 2024...
SCHEDULED POWER INTERRUPTION
Septembre 18, 2024, (Miyerkules nga adlaw)Alas 5:00 tubtob 7:00 sang agaAng CAPELCO magapatigayon sang pag ilis sang insulator kag correction sang line.Apektado nga Lugar:Whole Feeder 4R - San Roque Extension, New Fus, Mercedez Hotel, Sky Garden Hoel, Portion of...
Other News
[UPDATED] SCHEDULED POWER INTERRUPTION
Alas 8:30 sang aga tubtob 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag...
SCHEDULED POWER INTERRUPTION
Alas 8:30 sang aga tubtob 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag...
CONSOLIDATED TEAM ACCOMPLISHMENTS ML2
September 24-26, 2024, Tuesday to Thursday #TeamLarryAcejo ML 2 Team Members: L Acejo, E Dublado,...
INSTALLING HOUSEWIRING FOR SEMA BENEFICIARIES
September 26, 2024, Thursday Barangay Dinginan, Roxas City As the Socialized Energization of...
SCHEDULED POWER INTERRUPTION
Septembre 27, 2024 (Biyernes nga adlaw)Alas 8:30 sang aga tubtob 5:00 sang hapon.Ang CAPELCO...