(0963) 043 8339 info@capelco.com
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

July 8-12, 2024, Monday to Friday #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog with K Cordovero and R Distura, Jr. Accomplished: 1. Relocation of 2 units of 35 footer pole at Poblacion Dao Capiz. 2. Replacement of damaged...

read more
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11 Working Crew: #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, M Batuampo, J Degones and M Deocampo Accomplished: 1. Replacement of pole at Barangay Cagay, Roxas City 2. Replacement of pole at Barangay Cudian, Ivisan 3....

read more
CONSOLIDATED TEAM ACCOMPLISHMENTS ML2

CONSOLIDATED TEAM ACCOMPLISHMENTS ML2

#TeamLarryAcejo ML 2 Team Members: L Acejo, E Dublado, R Delfin, J Escalada and N Estorque Accomplished: 1. Line clearing at Barangay Mongpong to Barangay Gabuan, Roxas City 2. Line clearing at Barangay Dayao to Barangay Tanque, Roxas City 3. Line clearing at Barangay...

read more
POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

July 10, 2024, Wednesday Due to bad weather condition and technical problem in the distribution lines causing line faults, a number of emergency power interruptions occurred in different areas in Capiz within the territorial responsibilities of various area offices....

read more
SCHEDULED POWER INTERRUPTION

SCHEDULED POWER INTERRUPTION

HULYO 12, 2024 (Biyernes nga adlaw)Alas 8:30 sang aga tubtob Alas 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag Maintenance.LUGAR NGA APEKTADO: Barangay Sta. Fe, Casanayan, San Ramon, Balogo kag Dayhagan, Pilar.Gilayon man nga ibalik ang kuryente sa...

read more

Other News

Follow Us