The installation of the ground cables is almost complete and parallel to the work is the interconnection of overhead cables. The SF6 circuit breaker is now ready for testing subject for the confirmation of the National Grid Corporation of the Philippines. CAPELCO...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The work at Dao Substation continue as the crew are now laying down the cables for the interconnection of the 15 MVA power transformer. This is 15 hours of straight work already in time for the eventual energization by tomorrow and the restoration of power for the...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The New 15 MVA Power transformer has been properly positioned into its mounting platform and the area has been cleared of debris. Initial testing has been made and the result is positive. Working crews are now preparing the interconnections of its cable and all other...
PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION
Making use that power is out at Dao Substation, the construction crew conducted their own activities accomplishing the following: • Relocation of 3-Phase line at Sitio Utod, San Miguel, Dumalag (FB Complain) • Insertion of pole at Barangay San Miguel, Dumalag (C1...
PREPARATORY ACTIVITY FOR THE ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
Accomplished: 1. Installation of 1 span 3phase line @ Dao substation to energize Dao from Feeder 4 Panitan Substation via looping connection 2. Connection of jumper from 13.2 to 69 kV at bypass road Barangay Amaga, Sigma to energize Dao from Feeder 4 Panitan...
Other News
POST SCHEDULED POWER INTERRUPTION REPORT
As scheduled: From 5:00 AM to 6:30 AM In actual: From 5:01 AM to 6:06 AM Purpose: Reconfiguration...
ANG MALAIN NGA PANAHON ANG GINTUNAAN SANG MALAPNAGON NGA BROWNOUT
Suno sa impormasyon nga ginpaabot sang mga Area Offices sa Segundo Distrito, masyado kabaskog sang...
PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION
CAPELCO CONSTRUCTION CREWS Accomplished: 1. Relocation of 2 poles and rehabilitation of kilowatt...
SCHEDULED POWER INTERRUPTION
HUNYO 5, 2024 (Miyerkules nga adlaw)5:00 tubtob 6:30 sang agaAng CAPELCO magapatigayon sang pag...
MEMBER-CONSUMER-OWNER REQUEST ACTED
Sitio Utod, Barangay San Miguel, Dumalag Relocation of three-phase line Working Crew:...