PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION

PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION

Taking time that power is out due to the Preventive Maintenance Servicing of Dao Substation, CAPELCO’s construction crew and the maintenance crew of Dao Area Office conducted parallel activities to make use of the time that power is out. Accomplished: 1. Replacement...

read more
POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

From 4:11 AM to 8:58 AM Affected areas: Municipality of Sapian, Mambusao and Jamindan Chronology: • 4:11AM – Tripping off of 69 KV tapping point at Bangkal, Maninang affecting Sapian, Mambusao and Jamindan • 4:53 AM – Normalized all feeder lines • 5:50 AM – Tripping...

read more
MEMBER-CONSUMER-OWNER REQUEST ACTED

MEMBER-CONSUMER-OWNER REQUEST ACTED

Barangay Bula, Mambusao Accomplished: Relocation of pole Working Crew: #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog #TeamMAOMaintenance Team Members; E Taborda and L Llorente

read more
PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION

PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION

Taking time that power is out due to the Preventive Maintenance Servicing of Mambusao Substation and Tapping Point, CAPELCO’s construction crew and the maintenance crew of Mambusao Area Office conducted parallel activities to make use of the time that power is out....

read more