#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Installation of temporary 37.5 KVA transformer for the Barangay fiesta of Barangay Sto. Niño, Dumalag 2. Pole dressing of three-phase extension at bypass...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT1
#TeamTamtamDangan BT2 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes Accomplished: 1. Replacement of 3 pieces of rotten pole (mano-mano) at Sitio Malingin, Barangay Guintas, Jamindan 2. Relocation of pole and line clearing at Sitio Dodo,...
CONSOLIDATED TEAM ACCOMPLISHMENTS ML1
#TeamMakiBitoon ML-1 Team Members: M. Bitoon, J. Pinuela and E. Bithao Accomplished: Line clearing of Feeder M3 from CAPSU Barangay Pangabuan extension to Poblacion, Jamindan
CONSOLIDATED TEAM ACCOMPLISHMENTS BT2
#TeamKennyCordovero BT2 Team Members: K Cordovero, A Ferrer and R Distura Accomplished: Correction of grounding and installation of grounding at Feeder D-4, Barangay Timpas, Panitan
CONSOLIDATED TEAM ACCOMPLISHMENTS BT7
#TeamRamilDistura BT7 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Relocation of lines due to DPWH Road Widening Project and line clearing at San Roque Dumalag Capiz. 2. Pull out of idle materials at Barangay Agsilab,...
Other News
WEEKLY TEAM ACCOMPLISHMENTS BT 8
#TeamGeraldCondino BT 8 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 6
#TeamBobongSaron BT 6 Team Members: J Saron, F Fabella, M Batuampo, E Delos Santos and M. Deocampo...
CAPELCO SERVED AS RESOURCE PERSON IN THE SP COMMITTEE HEARING
Acting General Manager Engr. Edgar D. Diaz presented the perspective of an electric distribution...
CAPELCO 17TH TRI-MEDIA FELLOWSHIP 2024
Now on its 17th year, the annual tri-media initiatives of CAPELCO is an expression of its...
ECAR VI PARTICIPATED IN THE COORDINATION MEETING WITH NGCP
The electric cooperatives who are members of the Electric Cooperatives Association of Region VI...