(0963) 043 8339 info@capelco.com
JOINT TEAM ACCOMPLISHMENTS BT1, BT2 AND BT7

JOINT TEAM ACCOMPLISHMENTS BT1, BT2 AND BT7

Accomplished: Pull out of idle materials, transfer/rehabilitation of kilowatt hour meters and upgrading of transformer from 25 KVA to 37.5 KVA at Barangay Dangula, Dumarao Working crews: #TeamTamtamDangan BT1 Team Members: A Dangan, R Daliva, J Penuela, J Degones and...

read more
CONSOLIDATED TEAM ACCOMPLISHMENTS BT1

CONSOLIDATED TEAM ACCOMPLISHMENTS BT1

#TeamTamtamDangan BT1 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes Accomplished: 1. Installation of 2-span secondary line for health center and evacuation center at Barangay Tabun- acan. Pilar 2. Replacement of rotten pole, relocation of pole...

read more
CONSOLIDATED TEAM ACCOMPLISHMENTS BT9

CONSOLIDATED TEAM ACCOMPLISHMENTS BT9

#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Installation of 4-span secondary line and transfer/rehabilitation of kilowatt hour meters at Barangay Monteflor,Pilar 2. Insertion of intermediate pole...

read more
AGM MONTHLY MEETING NUMBER 3

AGM MONTHLY MEETING NUMBER 3

CAPELCO Burgos Street Office The monthly meeting with Acting General Manager Engr. Edgar D. Diaz was held earlier today of which employees that are based in Roxas City were treated to a presentation of the previous month’s accomplishments and the current month’s...

read more

Other News

Follow Us