MEMBER-CONSUMER-OWNER REQUEST ACTED
June 1, 2024, Saturday Sitio Utod, Barangay San Miguel, Dumalag Relocation of three-phase line Working Crew: #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R...
SCHEDULED POWER INTERRUPTION
HUNYO 9, 2024 (Domingo nga adlaw) 5:00 sang aga tubtob 2:00 sang hapon Ang CAPELCO magapatigayon sang Preventive Maintenance Servicing o PMS sang Burgos Substation. Lugar nga Apektado: FEEDER B1 – Crossing Petron to City Mall Arnaldo Boulevard, Burgos, Legaspi,...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT6
May 25, 26 and May 30, 2024, Saturday, Sunday and Thursday #TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes Accomplished: 1. Relocation of pole at Barangay Culajao Roxas City 2. Installation of intermediate pole at Barangay Ilamnay, Panay (FB...