CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

May 13-14, 2024, Monday to Tuesday #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Installation of 3 units of 37.5 KVA private transformer for Kerr Hardware at Barangay Poblacion, Tapaz 2. Installation of 3...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 9

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 9

May 14-15, 2024, Tuesday to Wednesday #TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Installation of temporary 37.5 KVA transformer at Sitio Bakante, Barangay Consolacion, Dumalag 2. Installation of...
JOINT TEAM ACCOMPLISHMENTS BT 6, ISUZU 2 AND ISUZU 5

JOINT TEAM ACCOMPLISHMENTS BT 6, ISUZU 2 AND ISUZU 5

May 12-15, 2024, Sunday to Wednesday #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo Accomplished: 1. Installation of 50 KVA transformer Spring Hills, Malocloc Sur, Ivisan 2. Uprating from 25 KVA to 37.5 KVA transformer at Banica,...
POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

May 15, 2024, Wednesday From 6:35 PM to 7:51 PMAreas affected: Feeder 4- Municipality of Sigma and portion of PanitanReason: Damaged insulator near Malapad Cogon Welcome RotundaResponding Crew: #TeamPAOMaintenanceTeam Members: C Guillermo and J...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT6

CONSOLIDATED TEAM ACCOMPLISHMENTS BT6

May 15, 2024, Wednesday #TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes Accomplished: 1. Rehabilitation of lines (Hole Digging) at Arocera Banica, Roxas City 2.Pull out 1 unit of 50 KVA temporary transformer at Baybay, Roxas City 3. Pull out...