MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
June 2, 2024 as of 6:00 AM today The installation of the ground cables is almost complete and parallel to the work is the interconnection of overhead cables. The SF6 circuit breaker is now ready for testing subject for the confirmation of the National Grid Corporation...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
June 1, 2024 as of 9:14 PM today The work at Dao Substation continue as the crew are now laying down the cables for the interconnection of the 15 MVA power transformer. This is 15 hours of straight work already in time for the eventual energization by tomorrow and the...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
June 1, 2024 as of 7:25 PM today The New 15 MVA Power transformer has been properly positioned into its mounting platform and the area has been cleared of debris. Initial testing has been made and the result is positive. Working crews are now preparing the...