PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
May 19, 2024, Sunday Taking time that power is out due to the Preventive Maintenance Servicing of Lawaan Substation, CAPELCO’s construction crew and the maintenance crew conducted parallel activities to make use of the time that power is out. Accomplished: 1....
POST SCHEDULED POWER INTERRUPTION REPORT
May 19, 2024, Sunday May 19, 2024, SundayChronology of Time and Areas affected:As scheduled: From 5:00 AM to 4:00 PMIn actual: From 5:05 AM to 2:25 PMReason: Conduct of Annual Preventive Maintenance Services (PMS) for Lawaan Substation.Areas affected:• FEEDER 1R-...
POST SCHEDULED POWER INTERRUPTION REPORT