CONSOLIDATED TEAM ACCOMPLISHMENTS BT6
May 15, 2024, Wednesday #TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes Accomplished: 1. Rehabilitation of lines (Hole Digging) at Arocera Banica, Roxas City 2.Pull out 1 unit of 50 KVA temporary transformer at Baybay, Roxas City 3. Pull out...
SCHEDULED POWER INTERRUPTION
MAYO 18, 2024 (Sabado nga adlaw) 5:30 sang aga tubtob 1:30 sang haponAng CAPELCO magapatigayon sang Preventive Maintenance Services (PMS) of Pres. Roxas Substation.LUGAR NGA APEKTADO: Tanan nga Feeder Lines nga konektado sa Pres. Roxas Substation:Feeder L1- Banwa sang...
NGCP PAID CAPELCO TSD A VISIT
May 13, 2024, Burgos Ilawod, Tanque, Roxas CIty Engineers of the National Grid Corporation of the Philippines (NGCP) paid CAPELCO Technical Services Department (TSD) a visit to discuss power grid scenario which is under their jurisdiction. As the grid operator, NGCP...