POST EMERGENCY POWER INTERRUPTION REPORT
May 3, 2024, From 1:27 AM to 4:37 AM Areas affected: Feeder – Municipality of Maayon with the exceptions of its upland barangays and portion of the Municipality of PanitanCuase: Broken and melted Insulator at Indayagan, MaayonCHRONOLOGYFrom 1:27 AM to 1:27 AM – First...
SCHEDULED POWER INTERRUPTION
MAYO 4, 2024 (Sabado nga adlaw)Ang CAPELCO mapatigayon sang pag ilis sang samad nga Insulators.1. ORAS: 5:45 sang aga tudtob 2:00 sang hapon.LUGAR NGA APEKTADO:-New Guia, Old Guia, Carataya, Jebaca, Cabungahan, Balighot, Indayagan, Quinat-uyan, Maayon.-Agloway kag...
COSOLIDATED POST SCHEDULED POWER INTERRUPTION REPORT