CONSOLIDATED TEAM ACCOMPLISHMENTS BT1

CONSOLIDATED TEAM ACCOMPLISHMENTS BT1

March 3 and March 5-6, 2024, Sunday and Tuesday and Wednesday #TeamTamtamDangan BT1 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes Accomplished: 1. Installation of 2-span secondary line for health center and evacuation center at Barangay Tabun-...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT9

CONSOLIDATED TEAM ACCOMPLISHMENTS BT9

March 5-7, 2024, Tuesday to Thursday #TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Installation of 4-span secondary line and transfer/rehabilitation of kilowatt hour meters at Barangay Monteflor,Pilar...
AGM MONTHLY MEETING NUMBER 3

AGM MONTHLY MEETING NUMBER 3

March 8, 2024, Friday CAPELCO Burgos Street Office The monthly meeting with Acting General Manager Engr. Edgar D. Diaz was held earlier today of which employees that are based in Roxas City were treated to a presentation of the previous month’s accomplishments and the...