October 20, 2024, Sitio Cubay, San Pedro, Pilar Working Team: #TeamTamtamDangan BT 7 Construction Crew Team Members: A. Dangan, R. Daliva, J. Doce, MA. Bolinas and PP Fuentes Accomplished: Replacement of 2 pcs. rotten poles and correction of...
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

October 19, 2024, Saturday As scheduled: From 6:00 AM to 3:00 PM In actual: From 6:00 AM to 11:58 AM, Howewer, Aglalana Dumarao was restored at around 2:40 PM Areas affected: Municipality of Dumarao and Barangays Mahunod-hunod and Putian, Cuartero Accomplished:...
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

October 19, 2024, Saturday As scheduled: From 6:00 AM to 3:00 PM In actual: From 6:00 AM to 11:58 AM, Howewer, Aglalana Dumarao was restored at around 2:40 PM Areas affected: Municipality of Dumarao and Barangays Mahunod-hunod and Putian, Cuartero Accomplished:...