POST EMERGENCY POWER INTERRUPTION REPORT
October 12-13, 2024, Saturday to Sunday From 11:22 PM to 11:28 PM Tripping off of Panitan-Roxas NGCP Transmission Line Areas affected: Whole of Roxas City with the exception of Adlawan, Liong, Loctugan, Bago and Olotayan From October 12, 2024 at 11:22 PM to October...
POST SCHEDULED POWER INTERRUPTION REPORT
October 12, 2024, Saturday As scheduled: From 6:00 AM to 3:00 PM In actual: From 6:00 AM to 2:55 PM Areas affected: Feeder D2 – Municipality of Dumalag and Tapaz Accomplished: Energization of new 3-phase line affected by DPWH Road Widening Project and line clearing...
COMPLETE HOUSEWIRING INSTALLATION OF SEMA BENEFICIARIES AT BARANGAY CABUGAO, ROXAS CITY
October 11, 2024, Friday Barangay Cabugao, Roxas City A total of fifty-four (54) beneficiaries of the Socialized Energization of Marginalized Applicants (SEMA) already received housewiring installation and is now ready to be energized. The Students who are undergoing...