POST SCHEDULED POWER INTERRUPTION REPORT
September 25, 2024, Wednesday As scheduled: From 8:30 AM to 4:30 PM In actual: From 8:30 AM to 4:21 PM Areas affected: • Barangays Bula, Najus-an, Bating and Pinay, Mambusao • Barangays Maninang, Bilao, Agtatacay Sur, Agtatacay Norte, Agsilab and Lonoy, Sapian. •...
POST EMERGENCY POWER INTERRUPTION REPORT
September 24, 2024, Tuesday From 7:15 PM to 10:00 PM Reason: Disconnected jumper due to broken insulator due to intrusion of gecko into the distribution line Actions taken: Replacement of broken insulator, replacement of power fuse and reconnection of jumpers Areas...
POST EMERGENCY POWER INTERRUPTION REPORT
September 24, 2024, From 8:21 PM to 8:44 PM Reason: Tripping off of NGCP Panitan-Sara 69 kV Transmission Line triggered by Under Frequency Relay (UFR) Switch. Areas Affected: FEEDER 1 (Municipality of Panay, portion of Panitan and Barangays Adlawan, Liong, Loctugan,...