POST SCHEDULED POWER INTERRUPTION REPORT
August 14, 2024, Wednesday As Scheduled: From 4:00 AM to 6:00 AM In actual: Feeder 2R – From 4:05 AM to 5:10 AM Feeder 4R – From 4:05 AM to 5:04 AM Reason: transfer of line connection of Barangay Tanza, Health Centrum at Barangay Banica and Barangay Bato to Feeder 2R....
POST EMERGENCY POWER INTERUPTION REPORT
August 13, 2024, Tuesday A series of major power interruptions occurred in Roxas City, Mambusao and Dao Area Offices owing to various causes mainly affecting the feederlines and other lateral connections. Major trouble in the line was the toppled electrical pole at...
POST SCHEDULED POWER INTERRUPTION
August 13, 2024, Tuesday As scheduled: From 8:00 AM to 4:00 PM In actual: From 8:02 AM to 3:21 PM Areas affected: Barangay Talon, Roxas City Reason: Line clearing operation Working Crews: #TeamMarkNain BT 6 Team Members: M Nain, G Datar, E Delos Santos and E Cainday...