POST EMERGENCY POWER INTERRUPTION REPORT
February 24, 2025, Monday Power Out: 9:39 am Power Restored: 9:57 am However, 3 phase line going San Juan, Baybay and Culasi, has no power due to a damaged pole top pin at San Juan, Baybay (near Tabai) Power Normalized: 10:40 am...
Accomplishment Report
February 22, 2025 (Saturday) ππππππππ ππ ππππππππππ ππ πππππ Pueblo de Panay, Lawaan, Roxas City Scheduled time to complete: π:ππππ – π:ππππ Actual time of completion: π:ππππ – π:ππππ The Technical Teams behind the successful operation and on-time...
ACCOMPLISHMENT REPORT
February 16, 2025 6:00 am to 11:52 am -Replacement of Rotten Pole -Replacement of rotten Cross Arms, – Replacement of defective insulators – Hotspot Correction and Line Clearing at Bailan, Jolongajog, Rizal & San Pedro, Pontevedra Successfully...
πππππππππ πππππ ππππππππππππ
Update: Time restored: 8:51 AM February 4, 2025 (Tuesday) Estimated Time duration: 1 hour Affected Areas: FEEDER 4: -(Portion of Brgy. Timpas, Panitan, Malapad Cogon, Parian and portion of Mianay, Sigma. -WHOLE MUNICIPALITY OF IVISAN Reason: REPLACEMENT OF DAMAGED...