POST SCHEDULED POWER INTERRUPTION
August 13, 2024, Tuesday As scheduled: From 8:00 AM to 4:00 PM In actual: From 8:02 AM to 3:21 PM Areas affected: Barangay Talon, Roxas City Reason: Line clearing operation Working Crews: #TeamMarkNain BT 6 Team Members: M Nain, G Datar, E Delos Santos and E Cainday...
POST SCHEDULED EMERGENCY POWER INTERRUPTION REPORT
August 13, 2024, Tuesday As scheduled: From 12:30 PM to 12:45 PM In actual: From 12:00 PM to 12:11 PM Reason: Hotspot Correction at Dao Substation. Areas affected: Whole Municipality of Dao and Barangay Bangonbangon,...
POST EMERGENCY POWER INTERRUPTION REPORT
August 13, 2024, Tuesday, From 10:55 AM to 11:36 AM Tripping off of 69KV transmission line at Sitio Bangkal, Maninang, Sapian due to intrusion of snake Areas affected: Municipalities of Mambusao, Sapian and Jamindan CHRONOLOGY: 10:55 AM – Tripping off of 69 KV line...
POST EMERGENCY POWER INTERUPTION REPORT
August 8, 2024, Thursday Earlier today, major power interruptions occurred in Roxas City, Mambusao, Dumalag and Dao Area Offices. One of which was largely due to the broken insulators resulting to line fault and affected the entire Feeder D4 where the Municipality of...