POST SCHEDULED EMERGENCY POWER INTERRUPTION REPORT
JUNE 28, 2024, Friday As scheduled: From 12:00 NN to 12:45 PM In actual: From 12:00 NN to 12:24 PM Areas affected: • Feeder 2 – Municipality of Pontevedra (except those those connected at President Roxas Substation), portion of Panay and portion of Panitan • Feeder 4...
POST EMERGENCY POWER INTERRUPTION REPORT
June 27, 2024, Thursday, from 8:33 PM to 9:10 PM Reason: Tripping off of Feeder 4R due to disconnected primary jumper of the three-phase line in front of Edgen Bakeshop, Banica Roxas City Areas affected: Feeder 4R – Barangay Banica, Tanza, Bato, Mongpong, Culajao,...
MEMBER-CONSUMER-OWNERS REQUEST ACTED
June 26, 2024, Wednesday West Lake Subdivision, Dayao, Roxas City Accomplished: Line clearing Working Crew: #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, J Degones, J Hachuela and M Deocampo Barangay Initan, Tapaz Accomplished: Relocation of pole Working...
CONSOLIDATED REPORT OF EMREGENCY POWER INTERRUPTION
June 26, 2024, Wednesday in various times MAMBUSAO AREA OFFICE Areas affected: • Whole municipality of Jaminadn ansd portion of Mambusao during the tripping off of Feeder M3 • Bunga, Mambusao • Aglibacao, Molit, Linambasan, Jaena Norte, Agloloway, Jaena Sur, Guintas...