PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION
June 2, 2024, Sunday CAPELCO CONSTRUCTION CREWS Accomplished: 1. Relocation of 2 poles and rehabilitation of kilowatt hour meters at Sitio Ayuyan, Barangay Sto. Angel, Dumalag 2. Replacement of rotten pole at Barangay Angub, Cuartero (Double circuit) and...
MEMBER-CONSUMER-OWNER REQUEST ACTED
June 1, 2024, Saturday Sitio Utod, Barangay San Miguel, Dumalag Relocation of three-phase line Working Crew: #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT6
May 25, 26 and May 30, 2024, Saturday, Sunday and Thursday #TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes Accomplished: 1. Relocation of pole at Barangay Culajao Roxas City 2. Installation of intermediate pole at Barangay Ilamnay, Panay (FB...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11
June 1-3, 2024, Saturday to Monday #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo Accomplished: 1. Assisted in the Roxas City scheduled power interruption at Barangay Adlawan and in Panay Area 2. Assisted in the Power interruption...